Article citation information:
Drábek, M., Pospíšil, J., Štěrba, R., Kříž, M., Heidu,
R.F. Tailor-made train path homogenization – a capacity improvement for mixed
rail traffic. Scientific Journal of
Silesian University of Technology. Series Transport. 2026, 132, 93-110. ISSN: 0209-3324. DOI: https://doi.org/10.20858/sjsutst.2026.132.5
Michal DRÁBEK[1],
Jiří POSPÍŠIL[2],
Roman ŠTĚRBA[3],
Milan KŘÍŽ[4],
Rudolf Franz HEIDU[5]
TAILOR-MADE TRAIN PATH
HOMOGENIZATION – A CAPACITY IMPROVEMENT FOR MIXED RAIL TRAFFIC
Summary. This article introduces a novel
segmentation of train paths, based on their degree of periodicity and
regularity, and, as a consequential measure, a framework process for local
mutual homogenization of periodic train paths for a more efficient rail capacity
utilization and for energy saving by avoiding an unnecessary stop of a freight
or passenger train to be overtaken by a faster train. The framework process is
tested in a timetable experiment on the prospective modernized mainline Praha -
Plzeň - Domažlice - Furth im Wald. The resulting timetable and distribution of
runtime surcharges show that the presented approach has great potential for use
in capacity coordination for mixed rail traffic. The types of railway lines and
timetables suitable for this framework process, as well as specific examples of
suitable lines on the current and future Czech railway network, are discussed
as well.
Keywords: heterogeneity, homogenization,
Integrated Periodic Timetable, interposition, railway capacity, speed bundling,
zero symmetry
1. INTRODUCTION
1.1. Strategic and Coordinated Railway Capacity
Planning in the EU
The need for more coordinated
railway capacity planning both within a particular mixed-traffic mainline, and
between the neighboring mainlines (especially
subsequent mainlines that form a corridor), requires a novel, holistic,
impartial approach that will take into the account technical capacity
requirements of all segments of railway transport, but, on the other hand, will
maintain the functionality of the (Integrated) periodic timetable for passenger
services, due to its undeniable benefit for sustainable traveling both within
particular states and through Europe.
Because the below proposed
segmentation of railway capacity and a framework process are meant to be
guidelines for the railway capacity allocators, rather that exact algorithms,
it is necessary to briefly introduce the political context of the EU in terms
of railway capacity planning, coordination, and allocation.
The liberalization of the European
railway market was first realized in freight transport. Afterwards, the
liberalization has gradually emerged in European passenger railways in two
forms. The first, more widespread form, is the operation of (often periodic)
regional or (sub)urban railway public transport services, but also
long-distance services in some countries – see for instance, Bulková et al. [1], ordered as a public service and either
periodically tendered or awarded directly, but not always to the dominant
national operator. The second form is purely commercial services (long-distance
as a rule), using the Open Access to the railway infrastructure in the EU.
After the success of the (at least
long-distance and suburban) passenger railway, good-quality capacity for the
freight trains (in the sense of frequent time windows for running
at maximum allowed speed without stops) became scarce on many European mainlines.
The European Commission responded by introducing the Rail Freight Corridors
(RFCs), based on the Regulation (EU) No. 913/2010 of the European
Parliament and of the Council of 22 September 2010 Concerning a European Rail
Network for Competitive Freight [8]. Recently,
the initial 11 RFCs have been redesigned into 9 new ones in accordance
with European Transport Corridors (ETCs) as a part of the revision of the
Trans-European Network [10]. The corridors are
administered by RailNetEurope (RNE) – the
association of national infrastructure managers and capacity allocators.
Particular corridors are then managed by the involved infrastructure managers
or capacity allocators [19]. The expectations for
RFCs were not fully met, as the European Commission states in paragraph 7
of the Proposal for a Regulation of the European Parliament and of the Council
on the use of railway infrastructure capacity in the single European railway
area, amending Directive 2012/34/EU and repealing Regulation (EU) No 913/2010 [9]: “The rules and
procedures on the management of rail infrastructure capacity should better
reflect the needs of all rail market segments. They should, in particular, take
into account the necessity of long-term stability of available capacity for
passenger services and of short-term flexibility for freight traffic to
respond to market demand. Therefore, the process of managing capacity
should no longer have a predominantly annual focus but should be arranged in
three subsequent phases of strategic capacity planning; rail service scheduling
and capacity allocation and adaptation and rescheduling of capacity. The
introduction of better-defined and structured phases that provide for the
possibility of long-term planning and short-term adaptation in capacity
management would particularly benefit services that are less easy to plan
in advance or are more complex to arrange, such as freight trains and
cross-border passenger trains.”
The strategy
of the European Commission, presented in this proposal, is reflected
in a Timetable Redesign (TTR) process, introduced by RNE. The main
idea is to fruitfully combine multi-year stability of mostly periodic
passenger services and some (partially international) freight trains with the
necessary flexibility of daily train path allocation for another (mostly ad hoc
freight) trains from the rest capacity. The TTR process comprises several
phases with gradually increasing levels of detail. The Capacity Strategy
comprises international alignment on large capacity restrictions (extended
track closures, etc.). In the Capacity Model, capacity volumes are assigned to
the identified market needs. Further, the processes analogous to present
capacity allocation and timetabling follow, but with the enhanced IT support
that enables better coordination between infrastructure managers and capacity
allocators [20].
The authors believe that the Capacity Model can (and
should) include the model timetable for the already known demand – mostly
periodic passenger services or suitable periodic freight train paths (PFTPs)
based on the known freight demand.
1.2. Scope and Structure of this Paper
This paper deals with capacity
planning in strategic and tactical phases. Thus, requirements for attractive
offers of various segments of (mainly periodic) passenger services and
energy-efficient timetabling of freight trains have to be integrated into the
planning process. Operative (ad hoc and daily) capacity allocation is
considered only in the form of delimitation of time windows for flexible
capacity allocation. Punctuality and timetable stability are not directly
addressed here – only in terms of sufficient time surcharges and buffer times
and their distribution along the mainline.
This paper is organized as follows.
In the Introduction, the European strategy for long- and middle-term
coordinated railway capacity planning was briefly mentioned. Then, a literature
review of the relevant publications is conducted, and the research gap is
derived. In Materials and Methods, the authors propose original segmentation of
train paths and rest capacity in accordance with the Proposal for a
Regulation of the European Parliament and of the Council on the use of railway
infrastructure capacity in the single European railway area, amending Directive
2012/34/EU and repealing Regulation (EU) No 913/2010 [9], with symmetrical periodic core, based on degree of periodicity and
regularity - both passenger train paths, adhering to the principles
of Integrated Periodic Timetable (IPT), and zero-symmetrical PFTPs.
Further, the authors propose a novel framework process for coordinated mutual
homogenization of train paths in the bottleneck sections for increased
efficiency of the capacity allocation and traction energy saving. This section
ends with a brief presentation of the mainline chosen for the timetable experiment
- the prospectively modernized mainline
Praha - Plzeň - Furth im
Wald (Germany). Then, the resulting symmetrical periodic timetable,
supplemented with PFTPs, constructed as a timetable experiment
in accordance with the presented framework process, is presented. In the
discussion, the proposed train path segmentation, a framework process, and
timetabling experiment are interpreted and then discussed. The
conclusion summarizes
contribution and major findings of the introduced framework approaches,
followed by recommendations for further research.
2. LITERATURE REVIEW
2.1. Timetabling and Capacity Allocation for
Mixed Traffic
Due to abundance of research in the
field of railway timetabling, the authors basically limited the literature
review to mixed railway traffic – scheduling of both passenger and freight
traffic on the same line, and to homogenization of train paths.
The first edition of UIC Code 406
Capacity [25] identified heterogeneity of train paths (i.e., different
scheduled section runtimes) as one of four key parameters that influence
railway capacity. The higher heterogeneity, the lower the capacity of the line.
This applies not only to double-track lines, but also to single-track lines –
see Dingler et al. [7].
The second edition of UIC Code 406
Capacity [26] clearly displayed limitations of capacity estimation based on the
compression of subsequent train paths closely together (with time supplements
added to secure quality of operation). This estimation gives various results,
depending on the chosen length of the line section.
Krýže [14] in his doctoral thesis
highlighted interdependencies between periodic timetables and railway capacity
(consumption). Further, he discussed potential usage of the optimization models
and finally proposed and demonstrated his own methods for complex construction
of periodic timetables. He, however, focused on shorter line sections and
did not deal in-depth with overtaking of freight trains by fast passenger
trains. In his thesis, he clearly illustrated and explained the influence of
train path heterogeneity, i.e., difference in sectional runtime of a train
against the most frequent segment of trains – the higher absolute value of the
difference, the lower the number of trains can be scheduled through the section
– see Fig. 1.
Fig. 1. Usable
capacity (sizes of time window) for trains with different section runtimes in
the context of periodic timetable on a double-track line [14],
translated into English by the authors
Janoš and Kříž [12] proposed to gain
additional capacity on a double-track mainline by active overtaking
(without stopping any train) a slow regional passenger train by a fast freight
train, given the speed ratio of both trains is high enough.
Caimi et al. [3] proposed a
mathematical formulation of partially periodic service. Thus, some train paths
can repeat periodically, but they can be scheduled in peak times only. Such
train paths can then alternate with other ones (e.g., freight train paths),
supposing that all such train paths can fit into an all-day, fully periodic
timetable.
Smoliner [22] dealt with the coexistence of
a nationwide IPT-based timetable, the infrastructure improvements derived
therefrom, and commercial (Open Access) passenger services. He proposed System
train Paths (STP) in the form of a parallelogram (with fixed departure and
arrival times in node stations, nevertheless enabling a variety of stopping
patterns in between) that can be either tendered as a public service or
tendered to commercial operators.
2.2. Coordination of Periodic Passenger
Timetable with Freight Train Paths or Capacity
Lindner and von Redern
[15] found that it was necessary to let periodic time windows (“canals”) within
the passenger periodic timetable be free for freight trains, giving them
sufficient capacity, and that such time windows on neighboring
railway lines should preferably be connected together to enable the running of
a freight train without stopping. Their conclusion was that periodic capacity
rather than a periodic timetable made sense for freight trains.
Stähli [23] considered that planning of
through or long-distance freight train paths should be already planned as
periodic, in coordination with passenger timetable – not only for the sake
of systematization of timetables, but also for better capacity utilization.
Čapek [6] (in cooperation with Swiss
rail infrastructure manager SBB Infrastruktur)
developed a software tool called FlexFahrplan for
planning timeslots for freight trains more rapidly and with better capacity
utilization. For this purpose, he developed an algorithm for speed bundling of
freight train paths with passenger (or another already allocated) train paths.
Čapek [6] and Klabes
[13] used intentional lengthening of train runtime to homogenize the train
paths for the sake of more efficient utilization of rail capacity.
Some authors distinguished different
capacity consumption of running through and stopping (or acceleration) of a
freight train in their research. Opitz [17] formulated “template train atoms”
differing in stopping or passing process - later referred to as “snippets” by Pöhle [18]. Vromans [28] saw this
variance as flexibility for his model, so the optimal location
of overtaking stations for freight trains could be determined. Another
aspect to be considered is the difference in (locomotive) power to hauled
mass ratios by freight train – see Fig. 2.
Fig. 2. Illustration of the difference in a practically usable capacity (sizes of time
window) for freight trains with higher and lower power to hauled mass ratios
that have to stop in both stations that delimit the section
Buschbacher [21] proposed targeted
“mini-invasive” infrastructure improvements in the form of adding a short third
track or lengthening a station track to enable smoother overtaking of a
regional train by an additional long-distance train. He used the same approach
for targeted overtaking of freight trains, and, in addition, proposed a
systematic rear-end assistance for freight trains to improve their acceleration
and, this way, decrease the capacity consumption.
2.3. Research Gap
To the authors’ knowledge, there
exists no procedure for iterative and coordinated planning of railway
capacity with zero-symmetrical, periodic core that takes needs (legitimate
interests) of passenger long-distance (with high-speed services, if need be),
agglomeration (suburban), regional, and freight railway into account and is
based on tailor-made homogenization of train paths for both passenger
(long-distance and local) and freight trains.
3. MATERIALS AND METHODS
3.1. Requirements for
Train Paths by Various Segments of Railway Transport
A network offer of long-distance
railway services should be, at least in the case of a country with polycentric
settlement, based on Integrated Periodic Timetable. Of course, in the largest
cities, there should be designed efficient interchange connections between
relevant long-distance public transport lines. But, in the regional centers, where most railway public transport lines operate
hourly, the local IPT-nodes (or “rendezvous” nodes), either around minute zero
or around minute 30, have to be respected even by express public transport
lines, which use high-speed railway lines for a significant portion of the
length of the particular public transport line. Moreover, an exact
interposition of two hourly public transport lines (with the same section
runtimes and stopping pattern) on a common section is suitable both for the
offer of services with a half period, and for efficient utilization of railway
capacity – it enables better coordination with agglomeration services, whose
period of a public transport line is often 30 min (at least for larger
agglomerations with approximately half a million inhabitants or more).
For a network offer of agglomeration
(or suburban) passenger railway services, maintaining the principles of IPT is crucial as well. Outside
of the center, the services should fit in
(long-distance or regional) IPT-nodes (rendezvous nodes). For the services
where daily commuting is predominant, a regular period is inevitable – the
smaller period, the more attractive for the passengers. Thus, for long parallel
sections of two or more public transport lines, their exact interposition into
half (or quarter) periods should be strived for. Because a public transport
line layout with a majority of diametral lines is both more economically
efficient (longer average mileage of the motor units) and more attractive for
the passengers, suitable time windows for running on more adjacent corridors
have to be found – in the needed period and with zero symmetry, to enable equal
timetable offers in both directions. If suitable interoperable (usually
tailor-made) vehicles are available, suburban train services can also be
directly connected to tram lines in the form of tram-trains – see, for
instance, Metelka and Janoš [16].
Regional train services (outside the
densely populated areas) on mainlines differ from the agglomeration services in
more ways – the trainsets are usually shorter, the service periods longer (60
or 120 min as a rule), and the average distance between neighboring
stops should be longer, due to both the lower population density of the
served area and for the sake of avoiding too frequent overtaking by
long-distance trains.
A special subset of regional or
agglomeration trains are regional express services, whose stopping pattern can
be zone-specific: in the inner (agglomeration) zone, the service either does
not stop at all or only at the most significant stops (in terms of passenger
demand and/or network interconnections). On the other hand, in the outer zone,
this service stops usually everywhere. This approach gives two benefits: a
travel time from the stop to the center mostly does
not exceed one hour, and the “fast” part of the train path can be easily
bundled with long-distance or freight services. A model of the system split of
passengers (between the everywhere stopping regional train and a regional
express) was introduced by Vávra and Janoš [27].
Even though the (Integrated)
periodic timetable is mostly not suitable for freight trains, the freight
operators need a flexible offer of suitable capacity in the railway network. It
means both an all-day regular offer of train paths and their flexible connections
in nodes, without unnecessary stops, in more directions. Further, if a freight
train has to stop (mostly to be overtaken by a faster long-distance
train), it should not be in, or before, an uphill section (for the sake of
energy saving), and it should not be in a capacity bottleneck, because braking
and subsequent acceleration of a freight train secondary consume a scarce
capacity – see Fig. 2.
3.2. Segmentation of
Train Paths Based on their Periodicity and Regularity
The authors have deliberately chosen
a soft methodological approach, albeit with preservation of basic mathematical
rules, that is necessary for Integrated Periodic Timetable. These rules are
commonly formulated as follows.
The first mathematical rule is a
unified period of services. The basic period is 60 min, and all derived periods
have to fulfil the following equation:
|
|
|
(1) |
where i and j
and k are indices, and p is a period.
The second rule is the unified
symmetry of all periodic train paths (for all pairs of periodic train paths,
for all node stations and directions, the difference between the arrival time
from the direction A to the station S and the nearest later
minute zero, is equal to the time distance between this minute zero, and the
nearest departure time from the station S to the direction A for
the same periodic train path in the opposite direction).
The third rule is the arc equation:
|
|
(2) |
where A
and B are IPT-nodes, and p is a period.
The fourth rule is the cycle equation:
|
|
(3) |
where A, B and C are
IPT-nodes, and p is a period.
This paper, however, deals with
capacity coordination within corridors, so the cycle equation has no practical
use here. Except for the abovementioned rules, the methodological approach is
soft, suitable more for practical management – planning and allocation – of
railway capacity by an infrastructure manager (or a capacity allocating body,
if it is a separate entity).
In accordance with the EU strategic
approach for railway capacity allocation [9] that emphasizes both multi-year
stability for longer-time train services and more flexibility for unpredictable
freight (and other) train services, and on the basis of requirements
described in the sub-chapter 3.1, the authors propose following segmentation of
freight train paths. Assuming that at least in Central Europe there prevail,
passenger services based on IPT, the authors propose the all-day (approx. 5:00
to 22:00) strictly periodic and symmetrical core of capacity, which should as
well include PFTPs – both pre-arranged (PaPs) and
further allocated, either for the annual timetable or otherwise (Rolling
Planning as mentioned in the TTR processes [20] or daily allocation).
Another segment of train paths
should be the edge of periodic capacity consumption – train paths that can be
partially periodic (e.g., additional peak passenger services) but are not
allocated all-day long, and thus can be alternated in off-peak times by other
train paths (e.g., freight) if possible. For a detailed mathematical
description of partial periodicity in the timetabling, see Caimi et al. [3].
The third segment is fully flexible
train path allocation.
The proposed train path segmentation
is displayed in Fig. 3.
Fig. 3. Proposal for segmentation of train
paths, based on their degree of
periodicity and regularity
3.3. Tailor-made Local
Homogenization of Periodic Train Paths
The aim of the homogenization of the
periodic train paths is better capacity utilization – to enable an additional
train path between two actual ones, which should help to save traction energy
by avoiding the otherwise necessary stop of a freight train. Similarly, a local
train path homogenization can avoid the overtaking of a passenger train by a
faster train, that wastes the time of the passengers.
The authors propose the following
framework process – a set of measures for the tailor-made local train path
homogenization in the sections that emerge as bottlenecks, depending on the
type of railway operation and the prevailing (the most frequent) segment of
railway transport in a particular section. To the authors’ knowledge, this is
the first framework process that recommends different measures for train path
homogenization in accordance with the type of railway operation. The measures
are summarized in Tab. 1 (++ stands for
substantial increase of the scheduled runtime, -- stands for reduction of stops
of the local trains, + and – stand for slight adjustments of runtime
surcharges).
In general, the proposed framework
process for tailor-made local train path homogenization can be applied on any
line, regardless of the number of tracks, with at least two segments of railway
transport whose average speed differs in a particular section. On a
single-track line, a full train path homogenization (of long-distance and
regional trains, or of passenger trains and PFTPs), complemented by an
interposition into a half period, leads to a concentration of crossing (meeting
trains in the opposite directions) into only a few stations, and thus to an
increase of available capacity for additional (or significantly delayed)
trains. For the lines with two or three tracks, the authors estimate that the
proposed framework process can bring significant capacity improvements
on the lines with a maximum speed of at least 140 km/h (actually regularly
utilized by some train segments), which is allowed continuously on the section
at least a few tens of kilometers long.
Tab. 1
Proposed framework process (a system of measures)
for local train path homogenization
|
Segment of trains Prevailing trains / type of operation |
Long-distance and fast regional passenger
trains |
Local (agglomeration and/or regional)
passenger trains (stopping everywhere) |
Freight trains / train paths |
|
Node area – mixed traffic |
none |
- |
none |
|
Hilly terrain, curvy line, mixed traffic
(speed limit up to approx... 100 km/h) |
none |
- |
none |
|
Mixed traffic, prevailing local trains
(speed limit up to 160 km/h) |
+ |
-- |
++ |
|
Mixed traffic, prevailing long-distance
trains (speed limit up to 160 km/h) |
+ |
-- |
- |
|
Single-track, at least 2 segments of railway
transport |
+ |
- |
- |
|
Freight bypass lines in large node areas |
not relevant |
not relevant |
++ |
|
Higher speed, long-distance trains (speed
limit 200 to 250 km/h) |
none |
not relevant |
- |
3.4. Chosen Railway
Lines and Passenger Timetables
For the timetable experiment that
should verify the framework approach presented in Tab. 1, two adjoining
lines were chosen: Praha - Beroun - Plzeň (Pilsen) and Plzeň - Domažlice - Furth im Wald
(Germany). On both lines, partial modernizations are planned – for the first
line, a completely new base tunnel between Praha-Smíchov
and Beroun stations for mixed long-distance, fast
regional and freight traffic for the speed up to 200 km/h is projected. For the
second line, partial modernization for the speed up to 200 km/h, that includes
doubling of the track, is projected. However, there should remain a
single-track section in the middle.
The projected line is schematically
illustrated in Fig. 4. The abbreviations of the stations and junctions are
explained in Tab. 2. The timetable of passenger trains is taken from the
research project Efficient Operational Concept for Rapid Services [4]. Both
lines were modeled and the timetable within this
project was constructed in the academic/research license of the FBS/ iPLAN timetabling software [11]. The same software was used
as well for the timetable experiment, that included the construction of a PFTP
and slight adjustment of one public transport line of fast trains – R30 –
and one public transport line of regional trains – REx40.
Fig. 4. Layout
of the prospectively modernized mainline Praha - Plzeň
- Furth im Wald (Germany) with the new tunnel between
Praha and Beroun and the modernized sections Plzeň - Holýšov and Blížejov - Domažlice
Tab. 2
Abbreviations
of the relevant stations and junctions
|
Abbreviation |
Name |
Abbreviation |
Name |
|
PRHL |
Praha main station |
STOD |
Stod |
|
PRSM |
Praha-Smíchov |
HOLY |
Holýšov |
|
QYODTV |
Tunnel VRT junction |
STAN |
Staňkov |
|
BERO |
Beroun |
QYBLJ |
Blížejov junction |
|
ZDIC |
Zdice |
DMZL |
Domažlice |
|
KARI |
Kařízek |
DOMM |
Domažlice mesto junction |
|
ROKY |
Rokycany |
CKUB |
Česká Kubice |
|
PZHL |
Plzeň main station |
XNFW |
Furth im Wald |
Passenger train paths, especially
the long-distance ones, were relatively strictly determined by symmetry
times to be achieved in the IPT-nodes. For the express segment (not stopping
between Praha and Plzeň), it was the IPT-node Plzeň in the minute 00 (line R32 and regional expresses to Domažlice město) and 30 (line
Ex6). The fast train line R30 had to achieve two regional IPT-nodes: Beroun in minute 00 and Rokycany in minute 30. Furthermore,
proceeding of all long-distance lines beyond Prague, as designed in the network
timetable for the horizon 2050 for the research project Efficient Operational
Concept for Rapid Services [4] determined possible time windows for their train
paths as well.
Longitudinal and speed profiles of
the railway line between Praha and Plzeň are
displayed in Fig. 5 and 6. For the railway line to Domažlice,
since it is a mix of a present railway line and newly constructed sections, the
longitudinal profile is difficult to obtain. The peak of this railway line is
in the station Česká Kubice
(CKUB).
The runtime surcharges for all
passenger public transport lines were chosen within the research project
Efficient Operational Concept for Rapid Services [4]. The initial periodic
passenger timetables from the abovementioned project are clearly displayed in
the form of a netgraph (public transport line
scheme with periodic arrival and departure times in the nodes) in Fig. 7.
In the Czech Republic, there is right-hand traffic on railways as well, so
the arrival and departure times to and from node stations are displayed in this
manner. The netgraph clearly shows exact
interpositions into the 30-minute period (Ex6+R32, R22+R26 and R30+Rex40 from
Praha to Beroun), and the approximate
interposition between Ex6 and regional expresses from Plzeň.
The times and numbers of stops marked by bold script will be slightly changed
in the following timetable experiment, resulting from local homogenization of
train paths in bottleneck sections.
For the sake of simplicity, the
possible future extension of the P21 public transport line (Nezvěstice
- Rokycany) to Plzeň was neglected.
Fig. 5. Longitudinal and speed profile of the prospective new tunnel between Praha
and Beroun (data: [4,11])
Fig. 6. Longitudinal and speed profile of the already modernized mainline Praha - Plzeň
(data: [4,11])
Fig. 7. Netgraph (scheme of periodic
passenger services) of the initial timetable on the prospectively
modernized mainline Praha - Plzeň - Furth im Wald – adapted from [4]
4. RESULTING SYMMETRICAL PERIODIC TIMETABLE
Due to a lack of available suitable
time windows left by the passenger train paths, a pair of stops for overtaking
by express trains between Praha and Furth im Wald had
to be designed. For the sake of saving the traction energy by freight trains,
and for the sake of train path symmetry, the stations for overtaking were
chosen so that there was always a small gradient in the relevant direction
behind them. According to the modernization project (Update of Feasibility
Study Plzeň - Domažlice –
CZ/DE border), lengths of the overtaking station tracks should be sufficient:
870 m in Staňkov and approximately 780 m in Stod
[24].
For the pair of PFTPs, the local
homogenization and adjustment of regional train paths were used as follows.
Only the direction from Praha to Furth im Wald is
described because for the opposite direction, the measures are (almost)
zero-symmetrical. The standard runtime surcharge for a PFTP, as used elsewhere
in the research project [4], was 10% (of technically minimum runtime,
calculated by the iPLAN software [11]).
In the section Praha - Beroun, the runtime surcharge for the PFTP was increased
significantly, to fit into a time window after a regional train (regional
express line REx40), but before the fast train to Zdice,
Písek and České Budějovice
(line R26).
Further, up to the station Rokycany,
the runtime surcharge for the PFTP was increased significantly as well, for the
sake of speed bundling with the (almost everywhere stopping) regional train.
The regional train path in this section had to be slightly adjusted by
decreasing the runtime surcharge to 6%.
From Rokycany, however, the runtime
surcharge for the PFTP was decreased to 3%, so that the freight trains would be
able to arrive at Plzeň hl.n.
(main station) before the Ex6 express line. The regional train path in this
section had to be adjusted as well, at first by decreasing the runtime
surcharge to 7%, and then by skipping the stop in Ejpovice.
The additional stop there with the R30 public transport line was designed
instead.
From Plzeň,
the runtime surcharge for the PFTP was decreased to 3%, up to the station Staňkov. Then, to Furth im Wald,
standard runtime surcharge of 10% for the PFTP was maintained.
The resulting graphical timetable
(train diagram) is displayed in Fig. 8. On the left edge, numbers of line
tracks (2 or 1) are clearly graphically marked. The timetable clearly shows the
bottleneck sections, where homogenization of passenger train paths was
necessary as well: Beroun (BERO) - Hořovice (HORO)
and Rokycany (ROKY) - Plzeň main station (PZHL).
Fig. 8. Proposed graphical
timetable for the modernized mainline Praha - Plzeň -
Furth im Wald (Germany) with the new tunnel between
Praha and Beroun and the modernized sections Plzeň - Holýšov and Blížejov - Domažlice [4]
Tab. 3 shows runtime surcharges by
section and for the direction there/back for all periodic train paths in the
resulting timetable, except the lines R26 and R32, which were neglected since
they occur on a relatively short section. For the proposed pair of PFTPs,
surcharges were chosen selectively, as proposed above in the sub-chapter 3.3.
So, between Rokycany and Stod, the freight train has to run at full speed – 100
km/h, because only a 3% runtime surcharge has been left. For such a distant
time horizon as 2050, the authors anticipate automatic Movement Authority for
a train and real-time automatic dispatching information for all locomotive
drivers even in the Czech Republic, so, in most cases, the driver would be
required only to slow down, but not to stop the train fully.
The resulting periodic train paths
(PFTPs are displayed in turquoise/light blue) are clearly illustrated in Fig. 9,
with the help of the netgraph – a scheme of public
transport lines (and PFTPs), where the single solid line stands for hourly
service or available capacity (in the case of PFTPs). The departure minutes
only by the PFTPs stand for passing through the station without stopping
in the particular minute.
The times marked by bold script were
slightly changed in the following timetable experiment, as a result of local
homogenization of train paths in bottleneck sections (compare with Fig. 7).
Tab. 3
Runtime surcharges of periodic train paths by
section (in percents of technically minimum runtime) direction there/back
from/to the particular station/junction
|
From/to the station (junction) |
Ex6 |
R32 |
Sprin-ter |
REx40 |
R30 |
RE
PZHL-DOMM |
Regio PZHL-STOD |
PFTP |
|
PRHL |
5/5 |
5/5 |
5/5 |
5/5 |
8/8 |
|
|
|
|
PRSM/QYODTV |
9/9 |
9/9 |
13/13 |
8/8 |
8/8 |
|
|
8/5 |
|
BERO |
10/8 |
7/7 |
13/13 |
6/6 |
8/7 |
|
|
36/30 |
|
ZDIC |
10/8 |
7/7 |
13/13 |
6/6 |
8/7 |
|
|
24/30 |
|
ROKY |
10/8 |
7/7 |
13/13 |
7/7 |
8/8 |
|
|
3/3 |
|
PZHL |
9/9 |
|
|
|
|
7/7 |
7/7 |
3/3 |
|
STOD |
9/9 |
|
|
|
|
7/7 |
|
3/3 |
|
STAN |
9/9 |
|
|
|
|
7/7 |
|
10/10 |
|
DMZL/DOMM |
6/6 |
|
|
|
|
|
|
10/10 |
Fig. 9. A proposed netgraph (scheme of periodic passenger services and freight
capacity - PFTPs) on the prospectively modernized mainline Praha - Plzeň - Furth im Wald adapted from Fig. 6
5. DISCUSSION AND CONCLUSIONS
To the authors’ knowledge, no such
holistic approach for such detailed, tailor-made mutual coordination of train
paths, considering a proposed symmetrical periodic core (IPT + PFTPs), but soft
enough to be universally implementable and to maintain flexibility in the
allocation of rest capacity, has been published so far. Because of prevailing
strictly mathematical timetabling research with several optimization criteria
and necessary simplifications of the real timetables and capacity allocation,
there remains a considerable gap between advanced railway timetabling and
operation research and practical railway capacity allocation process. The
deliberately chosen soft approach (nevertheless respecting mathematical
preconditions of IPT), that is based both on previous research and the original
authors’ findings, is therefore directly applicable for infrastructure managers
and other capacity allocating bodies, including the European Network of
Infrastructure Managers (ENIM), that should be established by the proposed
related Regulation of the European Parliament and of the Council 2023/0271(COD)
on the use of railway infrastructure capacity in the single European
railway area [9].
The above introduced timetable
experiment has clearly shown that with only slight adjustment of (regional)
passenger periodic train paths (1 to 2 minutes and one skipped stop) and with
feasible distribution of runtime surcharges, a pair of PFTPs with only one
overtaking on an approximately 150 km long, partially single-track, rail
corridor with busy passenger traffic, can be designed.
In the present Czech railway
network, the authors recommend considering the application of the above
presented framework process at least on following sections of present Czech
railway lines: Praha - (Poříčany) - Kolín - Pardubice - Česká Třebová - Olomouc - Ostrava, Praha - Benešov,
Brno - Břeclav and single-track lines Opava východ - Ostrava Svinov, Nymburk
- Mladá Boleslav and Bakov nad
Jizerou - Česká Lípa - Liberec. Further, the authors recommend considering
the application of the above presented framework process on the following
future Czech new or significantly modernized railway lines: Mladá Boleslav -
Liberec (a planned new line), new base tunnels Litoměřice
- Ústí nad Labem and Ústí nad
Labem - Heidenau with planned mixed traffic of
(high-speed) long-distance passenger trains and freight trains. However, in
such tunnels, any planned slowing of high-speed trains is out
of question.
Due to the complexity of the
proposed, highly iterative framework
process, and the considerable length of the mainline used in the timetabling
experiment, the authors had to neglect the assessment of timetable stability
and robustness. In general, a periodic timetable leads to locally high
consumption of the capacity, or tight scheduling of some trains after each
other, with almost zero buffer time (margin) above the minimum headway between
subsequent trains. Thus, the authors strongly recommend verification of
timetable feasibility for busy mainlines or nodes by suitable simulation tools
before their practical implementation – see for instance Čamaj
et al. [5].
As part of follow-up research, the
authors recommend focusing on the analysis and practical verification of the
accuracy of guiding freight trains into a conflict-free time slot, both during
timetable design and during operational traffic control. Unlike passenger
trains [2,29], freight trains require a longer reaction time – for example, for
the braking system – due to their greater length and weight.
References
1.
Bulková Zdenka, Jozef Gašparík,
Adam Torok, Martin Kendra, Rudolf Kampf. 2022. „Competitive Tendering for
Long-Distance Rail Transport Services as a Key to an Effective Rail Transport
Market”. SSRN. DOI: http://dx.doi.org/10.2139/ssrn.4162484.
2.
Cacchiani Valentina. Dennis
Huisman. Martin Kidd. Leo Kroon. Paolo Toth. Lucas Veelenturf. Joris Wagenaar.
2014. „An overview of recovery models and algorithms for real-time railway
rescheduling”. Transportation Research Part B: Methodological 63: 15-37.
ISSN: 1879-2367. DOI: https://doi.org/10.1016/j.trb.2014.01.009.
3.
Caimi Gabrio, Marco Laumanns, Kaspar Schüpbach, Stefan
Wörner, Martin Fuschberger. 2011. „The periodic service intention as a
conceptual framework for generating timetables with partial periodicity”. Transportation Planning and Technology 34(4): 323-339. ISSN: 1029-0354. DOI: https://doi.org/10.1080/03081060.2011.577151.
4.
Chýle Martin, Michal Drábek, Vít Janoš,
David Mikel, Jiří Pospíšil, Rudolf Vávra, Tomáš Záruba. 2023. „Síťový provozní koncept linek objednávaných MD pro Rychlá spojení”. STARFOS. Available at: https://takt.fd.cvut.cz/vyzkum.php. [In Czech: „Network
Service Concept for Lines Contracted by the Transport Ministry for High-Speed
Rail”.]
5.
Čamaj Juraj, Eva
Nedeliaková, Adrián Šperka, Lenka Ližbetinová. 2021. „The Planning of
Investment Activities in Field of Railway Transport with Support of Simulation
Tools”. Transportation Research Procedia 53: 39-49. ISSN: 2352-1465.
DOI: https://doi.org/10.1016/j.trpro.2021.02.005.
6.
Čapek K. 2004. „FlexFahrplan
- a new approach to railway operational planning”. Diploma thesis. Prague, Czechia: Czech Technical University in Prague.
7.
Dingler Mark H., Lai (Rex) Yung-Cheng, Christopher P. L.Barkan. 2009. „Impact of Train Type Heterogeneity on
Single-Track Railway Capacity”. Transportation Research Record:
Journal of the Transportation
Research Board 2117(1):
41-49.
8.
European Commission. 2010. Regulation (EU) No.
913/2010 of the European Parliament and of the Council of 22 September 2010
Concerning a European Rail Network for Competitive Freight. Brussels, Belgium: European Union.
9.
European Commission. 2023. Proposal for a
Regulation of the European Parliament and the Council on the use of railway
infrastructure capacity in the single European railway area, amending Directive
2012/34/EU and repealing Regulation (EU) No 913/2010. Brussels, Belgium: European Union.
10.
European Commission. 2024. Regulation (EU)
2024/1679 of the European Parliament and of the Council of 13 June 2024 on
Union guidelines for the development of the trans-European transport network,
amending Regulations (EU) 2021/1153 and (EU) No 913/2010 and repealing
Regulation (EU) No 1315/2013 (Text with EEA relevance). Brussels, Belgium: European Union.
11.
iRFP. „The Timetable
Construction System FBS”. Available at: https://www.en.irfp.de/the-timetable-construction-system-fbs.html.
12.
Janoš Vít, Milan Kříž.
2016. „Infrastructure Parameters Affecting Capacity of Railways in TEN-T”. In Interoperatibility of Railway Transport – IRICoN 2016: 22-25. Faculty of Transportation Sciences,
Czech Technical University in Prague, Prague, Czechia. 15 September 2016, Prague, Czechia. ISBN:
978-80-01-06022-3. DOI: https://doi.org/10.14311/APP.2016.5.0022.
13.
Klabes Sebastian Georg
2010. „Algorithmic railway capacity allocation in a competitive European
railway market”. PhD thesis. Aachen, Germany: RWTH
Aachen Univesity.
14.
Krýže Pavel. 2005. „Systematický jízdní řád a propustnost”. PhD Thesis.
Pardubice: Dopravní fakulta
Jana Pernera, Univerzita Pardubice. [In Czech: „Systmatic Timetable and Throughput”. PhD Thesis. Pardubice,
Czechia: Faculty of Transport Engineering, University of Pardubice].
15.
Lindner H. R., H.W. von Redern.
1989. „Güterzüge im Taktfahrplan-Möglichkeiten und grenzen”.
Die Bundesbahn 10: 867-874. ISSN: 0007-5876.
[In German: „Freight Trains in Clock-Faced Scheduling Timetables –
Possibilities and Limits”. The Federal Railway (magazine).]
16.
Metelka Stanislav, Vít Janoš. 2024. „Tram-train system
as a potential transport solution for the Olomouc Region”. Transport 39(1):
25-36. ISSN: 1648-3480.
17.
Opitz Jens. 2009. „Automatische
Erzeugung und Optimierung
von Taktfahrplänen in Schienenverkehrsnetzen”.
PhD Thesis. Dresden: Technische Universität Dresden.
[In German: „Automatic Generation and Optimization of Clock-Faced
Scheduling Timetables in Rail Transport Networks”. PhD Thesis. Dresden,
Germany: Dresden University of Technology].
18.
Pöhle Daniel. 2016. „Strategische Planung und Optimierung der Kapazität in Eisenbahnnetzen unter Nutzung von automatischer Taktfahrplanung”. PhD Thesis. Dresden: Technische
Universität Dresden. [In German: „Strategic Planning and Optimization of
Capacity in Railway Networks Using Automatic Clock-Faced Timetable Planning”.
PhD Thesis. Dresden, Germany: Dresden University of Technology].
19.
RailNetEurope, „Rail Freight
Corridors”. Available at: https://rne.eu/corridor-management/.
20.
RailNetEurope, „Timetable
Redesign”. Available at: https://rne.eu/capacity-management/ttr/.
21.
SCHIG. „Minimalinvasive Lösungsansätze zur besseren trassentechnischen Verträglichkeit von integralem Taktfahrplan, taktüberlagerten Personenfernverkehrszügen so wie Güterzügen”. Available at:
https://www.schig.com/fileadmin/Media/Blogs/2025/Minimalinvasive_Loesungsansaetze_zur_besseren_trassentechnischen_Vertraeglichkeit.pdf.
[In German: SCHIG.
„Minimally Invasive Solutions For Better Route-technical Compatibility Of
Integral Timetables, Timetable-overlain Long-distance Passenger Trains As Well
As Freight Trains”.]
22.
Smoliner Martin. 2021. „The
Integrated Timetable in Liberalised Railway Networks”. PhD thesis. Graz, Austria: Graz University of Technology.
23.
Stähli S. 1990. „Zur Entwicklung des Taktfahrplans in
der Schweiz”. Schweizer
Ingenieur und Architekt
50: 1464-1468. ISSN: 0251-0960. [In German: „On the development of the
clock-faced regular timetable in Switzerland”. Swiss Engineer and Architect.]
24.
SUDOP PRAHA, a.s. 2019. Aktualizace Studie proveditelnosti
Plzeň - Domažlice - st. hranice SRN. Praha: SUDOP PRAHA. Unpublished. [In
Czech: Updated Feasibility Study of Plzeň - Domažlice - Border with Fed. Rep. of Germany railway. Prague, Czechia: SUDOP PRAHA. Unpublished.]
25.
UIC Leaflet 406. 2004. Capacity, 1st edition.
Paris, France: International Union of Railways (UIC).
26.
UIC Leaflet 406. 2013. Capacity, 2nd edition.
Paris, France: International Union of Railways (UIC).
27.
Vávra Rudolf, Vít Janoš. 2025. „Service-Level Choice Modeling in Suburban Railway Transport”. In: 2025 Smart
Cities Symposium Prague – IEEE Proceedings. Faculty of Transportation
Sciences, Czech Technical University in Prague: Prague, Czechia. 29-30 May
2025, Prague, Czechia. ISBN: 979-8-3315-2550-7. DOI: https://doi.org/10.1109/SCSP65598.2025.11037707.
28.
Vromans Michiel J. C. M., Rommert Dekker, Leo G. Kroon. 2006. „Reliability and Heterogenity of Railway Transport”. European Journal of
Operational Research 172(2): 647-655. ISSN: 1872-6860. DOI: https://doi.org/10.1016/j.ejor.2004.10.010.
29.
Wang Entai. Yin Yuan. Pengli Mo. Andrea D’Ariano. Lixing
Yang. Ziyou Gao. 2025. „Real-time train rescheduling
optimization with combined cross-line strategies for urban rail network”. Transportation
Research Part E: Logistics and Transportation Review 201: 104210. ISSN:
1878-5794. DOI: https://doi.org/10.1016/j.tre.2025.104210.
Received 20.04.2026; accepted in revised form 02.07.2026
Scientific Journal of Silesian University of
Technology. Series Transport is licensed under a Creative Commons Attribution
4.0 International License
[1] Faculty of Transportation Sciences,
Czech Technical University in Prague, Konviktská 20,
110 00 Praha 1, Czech Republic. Email: xdrabek@fd.cvut.cz. ORCID:
https://orcid.org/0000-0002-0884-8765
[2] Faculty of Transportation Sciences,
Czech Technical University in Prague, Konviktská 20,
110 00 Praha 1, Czech Republic. Email: pospijir@fd.cvut.cz. ORCID:
https://orcid.org/0000-0001-5058-9958
[3] Faculty of Transportation Sciences,
Czech Technical University in Prague, Konviktská 20,
110 00 Praha 1, Czech Republic. Email: sterba@fd.cvut.cz. ORCID:
https://orcid.org/0000-0003-1088-4084
[4] Faculty of Transportation Sciences,
Czech Technical University in Prague, Konviktská 20,
110 00 Praha 1, Czech Republic. Email: krizmil1@fd.cvut.cz. ORCID:
https://orcid.org/0000-0001-8975-632X
[5] Faculty of Transportation Sciences,
Czech Technical University in Prague, Konviktská 20,
110 00 Praha 1, Czech Republic. Email: rudolf.heidu@fd.cvut.cz. ORCID:
https://orcid.org/0009-0008-4554-4630